Sunday, April 02, 2006

3/31/06 Tiling

3/31/06 The front door was delivered and installed today. No other new work. The water was hooked-up to the street. Perhaps this means the plumbers will come back next week.
3/30/06 Thursday, the tiling was finally completed in the kitchen backsplash and master bath. The central air conditioning units were delivered and installed today. The electrical fixtures were delivered today and stored in one of the closets.
3/29/06 Jason came by to talk to us about to resolve the master bath problem with the knee space. Also went over other stuff concerning the kitchen back splash by the desk area. The deck was completed today.
3/28/06 Rained today. Geronimo the tiler came late this afternoon to put grout on the foyer tiles. No other work done.
3/27/06 Deck was being started today. Looks small. Some work in the kitchen backsplash was done. The windows were cleaned inside and out over the weekend.