Wednesday, February 08, 2006

Exterior work - 2/8/2006


2/8/2006 Workers were putting wire mesh at the back of the house and black plastic covering. Some wire mesh was installed on the right side of the house. The left side is completely done.
2/7/2006 Workers have installed wire mesh on parts of the front, and left side of the house. Others are putting up the scaffolding in the back of the house. They poured the cement for the front porch. 2 workers were in the study removing wood from the ceiling. They have to replace the wood with a larger beam to secure the roof. Worker said this was caught by them and needed to be replaced in order to pass inspection.
2/6/2006 Workers started putting scaffolding up in front and the left side of the house preparing the sides for stucco.
2/4/2006 We covered up the ducts to prevent dust from the drywall. Also cleaned up sawdust in the wood crevices so that it doesn't get covered up by sheetrock.
2/3/2006 2 workers were drilling in the basement, what? I have yet to determine.