Thursday, March 09, 2006

Exterior painting done/Cabinets in 3/9/06




3/9/06 Work is progressing very well. Finally. Painting of the exterior is complete. They were doing retouch this morning. We like to color. It is better that we thought. They used Sherwin Williams' Chadwick and the accent is Swiss Coffee. The kitchen cabinets were being installed. Looks like the bathroom cabinets, laundry room were already done. Also, the wall texturing in the house is done! The doors were in place, looks like they were getting ready to install them. Also men were laying the trim to get started. The powder room cabinets are not stained but the cabinet installer said they were going to be stained later. Also I pointed out that one of the kitchen cabinets were suppossed to be a desk. Didn't I already point this out to them at least 10 times? At the end of the day, all the interior doors except for the main front door were in. All the trim upstairs and the shelving are in. Most of the trim downstairs were put in. The kitchen cabinets were all completely installed except for the desk in the kitchen and knee space in the MB bath. Luis the trim carpenter says he should be done by tomorrow Friday.
3/8/06 At lunch time, a man was putting sealants around the accents around the windows. Then by afternoon, they were painting the right side and back of the house! It is a very pretty color. One worker is spraying and 3 others were painting the accents. They were still sanding the spackle inside. Then by 3 pm a man was taping the inside of the windows by 5 pm Doug said they were already texturing the inside walls! Wow they were fast. I didn't even get to see them. And they had already painted most of the front, exterior. The interior doors, trim and cabinets were delivered today! Yey!
3/7/06 Spackling continues. They finished the 3rd layer of stucco. They have removed the scaffolding in front of the house. Why? When this is needed for painting. They also started clearing the lots across the street to the beginning of the cul-de-sac.

Tuesday, March 07, 2006

3rd Layer Stucco/Spackling 3/6/06


3/6/06 3rd layer of stucco complete in the front, left and right sides and behind sunroom and kitchen. Spackling continues and worker says they should be done tomorrow (3/7), then texturing on 3/8. Received a call from Jeff and Jeff to let us know that painting of inside and outside will begin the end of this week.
3/4/06 Sat. Workers were there spackling, putting the corner strips for walls and windows then spackling over them. Men were on stilts and the kids watched them work on them. We notice that the extra band around the garage columns and the gameroom box below columns were missing.
3/3/06 Workers continued to spackle and tape the house; exterior workers applied stucco on right side of house including right side front of house. By end of week, all of front, left side and right side was complete. More outrageous stressfull news! At lunch today, the workers were kicking football around the garage, a makeshift ball made of red tape used for taping plastic on the windows, at the end of the day, they had put a hole in the garage wall!!!!! Boy was I mad!
3/2/06 Workers started taping and spackling the house. Started applying the 3rd layer of stucco which is this white cement applied by hand to put additional texture to the house. Started on left side front and left side of house.
3/1/06 No inside work today as the inspector came and approved the wall board (drywall). Inspection must pass prior to taping/spackling.
2/28/06 Finished drywalling the garage today.
2/27/06 Inspector came but drywall was not complete. Delivered more drywall for the garage. 2nd layer of stucco was completed today.