Friday, March 24, 2006

3/24/06 Tiling






3/24/06 Three men were tiling, one in the boy's bath, one in the kitchen and one in the foyer. At end of the day, kitchen, girl's bath and boy's bath were completed. Earlier in the morning, men were removing the wood around around the driveway.
3/23/06 Men finished laying the thin set or wonder board in order to lay the tiles. At the end of the day, all the boards were laid. The sunroom and eat in kitchen have been tiled. It rained last night so some of the driveway brush lines were gone by morning. Told Ashhey about concern in MB knee space and in the powder room where the cabinet should be removed so that they could tile properly.
3/22/06 Some of the tiles were delivered and men started laying tiles in the master bath. Some men were installing a special board which was needed before laying the tiles. The driveway and front porch were poured today. The kids wrote their names by the driveway apron.
3/21/06 The granite in the kitchen, powder room and marble in the master bath were installed. It is gorgeous! I noticed then that the knee space was too tight in the master bath.
3/20/06 No work today. It had rained over the weekend so the driveway was not poured. Met our new project manager, Jason. Met with Ashley and Jason at the house to discuss many concerns and questions. This is where we had our status meeting.
3/17/06 The trim and doors were painted white! What a mess! Now the walls also have been painted white! And so have been the kitchen cabinets and the railing!