Monday, January 09, 2006

Electrical work begins 1/9/06

1/6/06 Electricians came to start putting in the electrical boxes, boxes for outlest, light switches, light fixtures, etc. Noticed that the last window was put in rear boy's room. In front boy's closet, we noticed that they framed the ducts too big that his closet has become so tiny. We opened a complaint ticket for this. At this time, rough plumbing has been completed.
1/5/06 The columns for the front of the house have been framed. The master bathroom tub has been framed including the ceiling to the toilet room.
1/2/06 We haven't been in the house in at least 2 weeks so here is the progress we noticed.
The roof shingles have been put in. The 2 back doors (main floor) have door knobs which lock from the outside; probably to deter people from walking out to the drop off since there is no deck yet. The arched windows in the sunroom and game room have been completly framed. The gas line has been installed (yellow hose). The plumbers were working when we got there. The tubs for the upstairs bathrooms are in. The master shower stall is in. The master bath windows were reframed and they had to rip off some outer sheathing as a result. Apparently, the plumbing started on 12/27/05 when we got a call while at Magic Mountain, CA.