Thursday, November 10, 2005

Basement Framing


11/3/05 Outside basement walls were framed.
11/8/05 The footings for the garage were poured and the steel plates were welded in on the basement floors.
11/9/05 The garage floors were prepared with steel mesh, plastic and sand. The steel posts were put in on the basement floors.
11/10/05 The steel beams for the basement were put in.